Microsoft Project - How to force one task to start immediately after another task finishes?












3














I am trying to force one task in Microsoft Project to start immediately after another task. However, each task has other dependencies, so a simple finish-to-start relationship or start-to-finish relationship won't always work. Below is a simplified example of my problem. I want to force Task 202 to start immediately after Task 201:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/20/12

Task 201, 1 day, predecessor 101 FS

Task 202, 1 day, predecessor 102 FS, 201 FS



Initial state



This arrangement works fine (Task 201 is completed on 2/21 and Task 202 is completed on 2/22) but if for some reason the predecessor Task 102 is bumped up to, say, 2/23/12 then Task 202 will be moved up as well, but 201 will stay put leaving a gap in between them. In this case, I could try rewriting the dependencies:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/23/12

Task 201, 1 day, predecessor 101 FS, 202 SF

Task 202, 1 day, predecessor 102 FS



Adjusted project schedule



Now Task 201 is completed over the day of 2/23, and Task 202 is completed on 2/24. However, if the predecessor task dates changed again, so that both are completed by the end of 2/20, then Task 202 will shift and actually start at the same time as Task 201 (since a start-to-finish relationship does not require that one task starts the same time another task finishes, but just that the dependent task cannot be completed until the primary task begins).



If there was some way to simply force the end time of Task 201 to equal the start time of Task 202, I believe this problem would be solved. However, for the life of me I cannot figure out how to do this.










share|improve this question
























  • Let me know if those screenshots aren't correct.
    – Der Hochstapler
    Feb 6 '12 at 14:15
















3














I am trying to force one task in Microsoft Project to start immediately after another task. However, each task has other dependencies, so a simple finish-to-start relationship or start-to-finish relationship won't always work. Below is a simplified example of my problem. I want to force Task 202 to start immediately after Task 201:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/20/12

Task 201, 1 day, predecessor 101 FS

Task 202, 1 day, predecessor 102 FS, 201 FS



Initial state



This arrangement works fine (Task 201 is completed on 2/21 and Task 202 is completed on 2/22) but if for some reason the predecessor Task 102 is bumped up to, say, 2/23/12 then Task 202 will be moved up as well, but 201 will stay put leaving a gap in between them. In this case, I could try rewriting the dependencies:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/23/12

Task 201, 1 day, predecessor 101 FS, 202 SF

Task 202, 1 day, predecessor 102 FS



Adjusted project schedule



Now Task 201 is completed over the day of 2/23, and Task 202 is completed on 2/24. However, if the predecessor task dates changed again, so that both are completed by the end of 2/20, then Task 202 will shift and actually start at the same time as Task 201 (since a start-to-finish relationship does not require that one task starts the same time another task finishes, but just that the dependent task cannot be completed until the primary task begins).



If there was some way to simply force the end time of Task 201 to equal the start time of Task 202, I believe this problem would be solved. However, for the life of me I cannot figure out how to do this.










share|improve this question
























  • Let me know if those screenshots aren't correct.
    – Der Hochstapler
    Feb 6 '12 at 14:15














3












3








3







I am trying to force one task in Microsoft Project to start immediately after another task. However, each task has other dependencies, so a simple finish-to-start relationship or start-to-finish relationship won't always work. Below is a simplified example of my problem. I want to force Task 202 to start immediately after Task 201:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/20/12

Task 201, 1 day, predecessor 101 FS

Task 202, 1 day, predecessor 102 FS, 201 FS



Initial state



This arrangement works fine (Task 201 is completed on 2/21 and Task 202 is completed on 2/22) but if for some reason the predecessor Task 102 is bumped up to, say, 2/23/12 then Task 202 will be moved up as well, but 201 will stay put leaving a gap in between them. In this case, I could try rewriting the dependencies:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/23/12

Task 201, 1 day, predecessor 101 FS, 202 SF

Task 202, 1 day, predecessor 102 FS



Adjusted project schedule



Now Task 201 is completed over the day of 2/23, and Task 202 is completed on 2/24. However, if the predecessor task dates changed again, so that both are completed by the end of 2/20, then Task 202 will shift and actually start at the same time as Task 201 (since a start-to-finish relationship does not require that one task starts the same time another task finishes, but just that the dependent task cannot be completed until the primary task begins).



If there was some way to simply force the end time of Task 201 to equal the start time of Task 202, I believe this problem would be solved. However, for the life of me I cannot figure out how to do this.










share|improve this question















I am trying to force one task in Microsoft Project to start immediately after another task. However, each task has other dependencies, so a simple finish-to-start relationship or start-to-finish relationship won't always work. Below is a simplified example of my problem. I want to force Task 202 to start immediately after Task 201:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/20/12

Task 201, 1 day, predecessor 101 FS

Task 202, 1 day, predecessor 102 FS, 201 FS



Initial state



This arrangement works fine (Task 201 is completed on 2/21 and Task 202 is completed on 2/22) but if for some reason the predecessor Task 102 is bumped up to, say, 2/23/12 then Task 202 will be moved up as well, but 201 will stay put leaving a gap in between them. In this case, I could try rewriting the dependencies:



Task 101, 1 day, starts 2/20/12

Task 102, 1 day, starts 2/23/12

Task 201, 1 day, predecessor 101 FS, 202 SF

Task 202, 1 day, predecessor 102 FS



Adjusted project schedule



Now Task 201 is completed over the day of 2/23, and Task 202 is completed on 2/24. However, if the predecessor task dates changed again, so that both are completed by the end of 2/20, then Task 202 will shift and actually start at the same time as Task 201 (since a start-to-finish relationship does not require that one task starts the same time another task finishes, but just that the dependent task cannot be completed until the primary task begins).



If there was some way to simply force the end time of Task 201 to equal the start time of Task 202, I believe this problem would be solved. However, for the life of me I cannot figure out how to do this.







microsoft-project project-management






share|improve this question















share|improve this question













share|improve this question




share|improve this question








edited Feb 7 '12 at 6:49









N.N.

1,11111631




1,11111631










asked Feb 6 '12 at 13:38









JLW

16112




16112












  • Let me know if those screenshots aren't correct.
    – Der Hochstapler
    Feb 6 '12 at 14:15


















  • Let me know if those screenshots aren't correct.
    – Der Hochstapler
    Feb 6 '12 at 14:15
















Let me know if those screenshots aren't correct.
– Der Hochstapler
Feb 6 '12 at 14:15




Let me know if those screenshots aren't correct.
– Der Hochstapler
Feb 6 '12 at 14:15










2 Answers
2






active

oldest

votes


















0














I saw something like this in another forum. You can paste dates as links which will allow you to fix a start-end date relationship.




  1. Copy the finish date from task 201

  2. Right-click the start date for task 202 and choose paste special

  3. Select the "Link" radio button and click OK


This should link the two together so that one changing will immediately update the other.






share|improve this answer





























    0














    You can use the Link Tasks option in the Schedule field which is already available in MS Project. Select one or more rows that you would like to apply this setting to and press the "link tasks" button. After that you can click the "Respect Links" button.



    Hope this will help.






    share|improve this answer





















      Your Answer








      StackExchange.ready(function() {
      var channelOptions = {
      tags: "".split(" "),
      id: "3"
      };
      initTagRenderer("".split(" "), "".split(" "), channelOptions);

      StackExchange.using("externalEditor", function() {
      // Have to fire editor after snippets, if snippets enabled
      if (StackExchange.settings.snippets.snippetsEnabled) {
      StackExchange.using("snippets", function() {
      createEditor();
      });
      }
      else {
      createEditor();
      }
      });

      function createEditor() {
      StackExchange.prepareEditor({
      heartbeatType: 'answer',
      autoActivateHeartbeat: false,
      convertImagesToLinks: true,
      noModals: true,
      showLowRepImageUploadWarning: true,
      reputationToPostImages: 10,
      bindNavPrevention: true,
      postfix: "",
      imageUploader: {
      brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
      contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
      allowUrls: true
      },
      onDemand: true,
      discardSelector: ".discard-answer"
      ,immediatelyShowMarkdownHelp:true
      });


      }
      });














      draft saved

      draft discarded


















      StackExchange.ready(
      function () {
      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f386530%2fmicrosoft-project-how-to-force-one-task-to-start-immediately-after-another-tas%23new-answer', 'question_page');
      }
      );

      Post as a guest















      Required, but never shown

























      2 Answers
      2






      active

      oldest

      votes








      2 Answers
      2






      active

      oldest

      votes









      active

      oldest

      votes






      active

      oldest

      votes









      0














      I saw something like this in another forum. You can paste dates as links which will allow you to fix a start-end date relationship.




      1. Copy the finish date from task 201

      2. Right-click the start date for task 202 and choose paste special

      3. Select the "Link" radio button and click OK


      This should link the two together so that one changing will immediately update the other.






      share|improve this answer


























        0














        I saw something like this in another forum. You can paste dates as links which will allow you to fix a start-end date relationship.




        1. Copy the finish date from task 201

        2. Right-click the start date for task 202 and choose paste special

        3. Select the "Link" radio button and click OK


        This should link the two together so that one changing will immediately update the other.






        share|improve this answer
























          0












          0








          0






          I saw something like this in another forum. You can paste dates as links which will allow you to fix a start-end date relationship.




          1. Copy the finish date from task 201

          2. Right-click the start date for task 202 and choose paste special

          3. Select the "Link" radio button and click OK


          This should link the two together so that one changing will immediately update the other.






          share|improve this answer












          I saw something like this in another forum. You can paste dates as links which will allow you to fix a start-end date relationship.




          1. Copy the finish date from task 201

          2. Right-click the start date for task 202 and choose paste special

          3. Select the "Link" radio button and click OK


          This should link the two together so that one changing will immediately update the other.







          share|improve this answer












          share|improve this answer



          share|improve this answer










          answered May 16 '13 at 17:55









          Jon

          1




          1

























              0














              You can use the Link Tasks option in the Schedule field which is already available in MS Project. Select one or more rows that you would like to apply this setting to and press the "link tasks" button. After that you can click the "Respect Links" button.



              Hope this will help.






              share|improve this answer


























                0














                You can use the Link Tasks option in the Schedule field which is already available in MS Project. Select one or more rows that you would like to apply this setting to and press the "link tasks" button. After that you can click the "Respect Links" button.



                Hope this will help.






                share|improve this answer
























                  0












                  0








                  0






                  You can use the Link Tasks option in the Schedule field which is already available in MS Project. Select one or more rows that you would like to apply this setting to and press the "link tasks" button. After that you can click the "Respect Links" button.



                  Hope this will help.






                  share|improve this answer












                  You can use the Link Tasks option in the Schedule field which is already available in MS Project. Select one or more rows that you would like to apply this setting to and press the "link tasks" button. After that you can click the "Respect Links" button.



                  Hope this will help.







                  share|improve this answer












                  share|improve this answer



                  share|improve this answer










                  answered Jan 21 '14 at 9:11









                  user291916

                  1




                  1






























                      draft saved

                      draft discarded




















































                      Thanks for contributing an answer to Super User!


                      • Please be sure to answer the question. Provide details and share your research!

                      But avoid



                      • Asking for help, clarification, or responding to other answers.

                      • Making statements based on opinion; back them up with references or personal experience.


                      To learn more, see our tips on writing great answers.





                      Some of your past answers have not been well-received, and you're in danger of being blocked from answering.


                      Please pay close attention to the following guidance:


                      • Please be sure to answer the question. Provide details and share your research!

                      But avoid



                      • Asking for help, clarification, or responding to other answers.

                      • Making statements based on opinion; back them up with references or personal experience.


                      To learn more, see our tips on writing great answers.




                      draft saved


                      draft discarded














                      StackExchange.ready(
                      function () {
                      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f386530%2fmicrosoft-project-how-to-force-one-task-to-start-immediately-after-another-tas%23new-answer', 'question_page');
                      }
                      );

                      Post as a guest















                      Required, but never shown





















































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown

































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown







                      Popular posts from this blog

                      flock() on closed filehandle LOCK_FILE at /usr/bin/apt-mirror

                      Mangá

                      Eduardo VII do Reino Unido