I'm installing a tankless water heater (150lbs static load, 10" deep)



I only have one option for installation and it is a 2x3 framed wall with 24" centers.



The Top bracket is designed to mount on top of a horizontal crossmember with screws penetrating the cross member in four locations and the studs in two. The bottom bracket requires a cross member as well but it just bolts to the cross member.



My question is this. What is the best way to install this right (without rebuilding the wall). Double jack studs would work if the actual dimensions were 2x3, which they are not. Should I just add another stud inside and work off of that?










share|improve this question






















  • Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
    – noybman
    3 hours ago















up vote
1
down vote

favorite












I'm installing a tankless water heater (150lbs static load, 10" deep)



I only have one option for installation and it is a 2x3 framed wall with 24" centers.



The Top bracket is designed to mount on top of a horizontal crossmember with screws penetrating the cross member in four locations and the studs in two. The bottom bracket requires a cross member as well but it just bolts to the cross member.



My question is this. What is the best way to install this right (without rebuilding the wall). Double jack studs would work if the actual dimensions were 2x3, which they are not. Should I just add another stud inside and work off of that?










share|improve this question






















  • Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
    – noybman
    3 hours ago













up vote
1
down vote

favorite









up vote
1
down vote

favorite











I'm installing a tankless water heater (150lbs static load, 10" deep)



I only have one option for installation and it is a 2x3 framed wall with 24" centers.



The Top bracket is designed to mount on top of a horizontal crossmember with screws penetrating the cross member in four locations and the studs in two. The bottom bracket requires a cross member as well but it just bolts to the cross member.



My question is this. What is the best way to install this right (without rebuilding the wall). Double jack studs would work if the actual dimensions were 2x3, which they are not. Should I just add another stud inside and work off of that?










share|improve this question













I'm installing a tankless water heater (150lbs static load, 10" deep)



I only have one option for installation and it is a 2x3 framed wall with 24" centers.



The Top bracket is designed to mount on top of a horizontal crossmember with screws penetrating the cross member in four locations and the studs in two. The bottom bracket requires a cross member as well but it just bolts to the cross member.



My question is this. What is the best way to install this right (without rebuilding the wall). Double jack studs would work if the actual dimensions were 2x3, which they are not. Should I just add another stud inside and work off of that?







framing mounting tankless






share|improve this question













share|improve this question











share|improve this question




share|improve this question










asked 3 hours ago









mreff555

291110




291110












  • Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
    – noybman
    3 hours ago


















  • Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
    – noybman
    3 hours ago
















Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
– noybman
3 hours ago




Do you mean to add 5 2x3's? Or 2 perpendicular (hint hint) ... or are you saying you'll add ONE full length to get the 16"? Any of those should work as long as its static and all points are well secured.
– noybman
3 hours ago










2 Answers
2






active

oldest

votes

















up vote
2
down vote













The other answer given so far describes a solution where the tankless water heater is being installed in an area where the studs are open and not covered. There are instances where the studs are not open and may be covered with drywall (a.k.a. sheet rock). It this instance the installation of extra studs or cross blocking is not so easy and other methods are called for. I will describe two options:




  1. You can cover the entire wall area where the brackets will be attached with a piece of 3/4" plywood. This may actually need to extend beyond the end of the bracket if the existing studs in the wall are farther away from the bracket mounting points. Secure the plywood to the wall surface using screws through the plywood and into the existing studding structure. Then mount the bracketing to the plywood. With proper size pilot holes for the screws the plywood does a really good job of holding the screws.

  2. An alternative solution would be to mount two horizontal 2x4s or 2x6s flat on the wall centered vertically where the tankless heater brackets will be located. These cross members are attached with screws at each existing stud location. They may have to extend longer than the width of the bracketing if the next stud is further over from the mounting location. Once the cross members are secured the bracketing can be screwed into the cross members.


Note: Either of these schemes can also be used on a wall that has open studs. In fact applying one of these techniques could even be easier to install than extra studs and blocking between existing studding.






share|improve this answer





















  • This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
    – noybman
    31 mins ago


















up vote
1
down vote













I would fit two 2x6 (or larger) blocks crossways between your studs at the two mounting locations. Put three 3" construction (not black drywall) screws through the studs into each end of the blocks. Pilot through the studs to avoid splitting. You won't need to pilot into the end-grain of the blocks unless they're very hard wood.



___________________________________
___________________________________
| |* | |* <-- toenail screws or angle brackets
| | | |
| | | |
| | | |
| |______________________| |
| | | |*
| | 2x6 block | |* <-- three screws
| |______________________| |*
| | | |
| | | |
| | | |


This will easily carry your heater. The only weakness at this point is the connection of each stud to the top plate. you might add toenailed screws or angle brackets there.



You could also lay in two 2x6 studs, flatwise, tight to each 2x3 stud in the bay where you'll mount the heater. This would give more horizontal stiffness if you feel like your studs are too flexible. Run screws through the 2x3 studs every foot or so.



___________________________________
___________________________________
| | | | | |
| | | | | |
| | 2x6 | | 2x6 | |
| | | | | |
| | | | | |





share|improve this answer























    Your Answer








    StackExchange.ready(function() {
    var channelOptions = {
    tags: "".split(" "),
    id: "73"
    };
    initTagRenderer("".split(" "), "".split(" "), channelOptions);

    StackExchange.using("externalEditor", function() {
    // Have to fire editor after snippets, if snippets enabled
    if (StackExchange.settings.snippets.snippetsEnabled) {
    StackExchange.using("snippets", function() {
    createEditor();
    });
    }
    else {
    createEditor();
    }
    });

    function createEditor() {
    StackExchange.prepareEditor({
    heartbeatType: 'answer',
    convertImagesToLinks: false,
    noModals: true,
    showLowRepImageUploadWarning: true,
    reputationToPostImages: null,
    bindNavPrevention: true,
    postfix: "",
    imageUploader: {
    brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
    contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
    allowUrls: true
    },
    noCode: true, onDemand: true,
    discardSelector: ".discard-answer"
    ,immediatelyShowMarkdownHelp:true
    });


    }
    });














    draft saved

    draft discarded


















    StackExchange.ready(
    function () {
    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fdiy.stackexchange.com%2fquestions%2f152798%2f16-center-bracket-to-24-center-framing%23new-answer', 'question_page');
    }
    );

    Post as a guest















    Required, but never shown

























    2 Answers
    2






    active

    oldest

    votes








    2 Answers
    2






    active

    oldest

    votes









    active

    oldest

    votes






    active

    oldest

    votes








    up vote
    2
    down vote













    The other answer given so far describes a solution where the tankless water heater is being installed in an area where the studs are open and not covered. There are instances where the studs are not open and may be covered with drywall (a.k.a. sheet rock). It this instance the installation of extra studs or cross blocking is not so easy and other methods are called for. I will describe two options:




    1. You can cover the entire wall area where the brackets will be attached with a piece of 3/4" plywood. This may actually need to extend beyond the end of the bracket if the existing studs in the wall are farther away from the bracket mounting points. Secure the plywood to the wall surface using screws through the plywood and into the existing studding structure. Then mount the bracketing to the plywood. With proper size pilot holes for the screws the plywood does a really good job of holding the screws.

    2. An alternative solution would be to mount two horizontal 2x4s or 2x6s flat on the wall centered vertically where the tankless heater brackets will be located. These cross members are attached with screws at each existing stud location. They may have to extend longer than the width of the bracketing if the next stud is further over from the mounting location. Once the cross members are secured the bracketing can be screwed into the cross members.


    Note: Either of these schemes can also be used on a wall that has open studs. In fact applying one of these techniques could even be easier to install than extra studs and blocking between existing studding.






    share|improve this answer





















    • This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
      – noybman
      31 mins ago















    up vote
    2
    down vote













    The other answer given so far describes a solution where the tankless water heater is being installed in an area where the studs are open and not covered. There are instances where the studs are not open and may be covered with drywall (a.k.a. sheet rock). It this instance the installation of extra studs or cross blocking is not so easy and other methods are called for. I will describe two options:




    1. You can cover the entire wall area where the brackets will be attached with a piece of 3/4" plywood. This may actually need to extend beyond the end of the bracket if the existing studs in the wall are farther away from the bracket mounting points. Secure the plywood to the wall surface using screws through the plywood and into the existing studding structure. Then mount the bracketing to the plywood. With proper size pilot holes for the screws the plywood does a really good job of holding the screws.

    2. An alternative solution would be to mount two horizontal 2x4s or 2x6s flat on the wall centered vertically where the tankless heater brackets will be located. These cross members are attached with screws at each existing stud location. They may have to extend longer than the width of the bracketing if the next stud is further over from the mounting location. Once the cross members are secured the bracketing can be screwed into the cross members.


    Note: Either of these schemes can also be used on a wall that has open studs. In fact applying one of these techniques could even be easier to install than extra studs and blocking between existing studding.






    share|improve this answer





















    • This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
      – noybman
      31 mins ago













    up vote
    2
    down vote










    up vote
    2
    down vote









    The other answer given so far describes a solution where the tankless water heater is being installed in an area where the studs are open and not covered. There are instances where the studs are not open and may be covered with drywall (a.k.a. sheet rock). It this instance the installation of extra studs or cross blocking is not so easy and other methods are called for. I will describe two options:




    1. You can cover the entire wall area where the brackets will be attached with a piece of 3/4" plywood. This may actually need to extend beyond the end of the bracket if the existing studs in the wall are farther away from the bracket mounting points. Secure the plywood to the wall surface using screws through the plywood and into the existing studding structure. Then mount the bracketing to the plywood. With proper size pilot holes for the screws the plywood does a really good job of holding the screws.

    2. An alternative solution would be to mount two horizontal 2x4s or 2x6s flat on the wall centered vertically where the tankless heater brackets will be located. These cross members are attached with screws at each existing stud location. They may have to extend longer than the width of the bracketing if the next stud is further over from the mounting location. Once the cross members are secured the bracketing can be screwed into the cross members.


    Note: Either of these schemes can also be used on a wall that has open studs. In fact applying one of these techniques could even be easier to install than extra studs and blocking between existing studding.






    share|improve this answer












    The other answer given so far describes a solution where the tankless water heater is being installed in an area where the studs are open and not covered. There are instances where the studs are not open and may be covered with drywall (a.k.a. sheet rock). It this instance the installation of extra studs or cross blocking is not so easy and other methods are called for. I will describe two options:




    1. You can cover the entire wall area where the brackets will be attached with a piece of 3/4" plywood. This may actually need to extend beyond the end of the bracket if the existing studs in the wall are farther away from the bracket mounting points. Secure the plywood to the wall surface using screws through the plywood and into the existing studding structure. Then mount the bracketing to the plywood. With proper size pilot holes for the screws the plywood does a really good job of holding the screws.

    2. An alternative solution would be to mount two horizontal 2x4s or 2x6s flat on the wall centered vertically where the tankless heater brackets will be located. These cross members are attached with screws at each existing stud location. They may have to extend longer than the width of the bracketing if the next stud is further over from the mounting location. Once the cross members are secured the bracketing can be screwed into the cross members.


    Note: Either of these schemes can also be used on a wall that has open studs. In fact applying one of these techniques could even be easier to install than extra studs and blocking between existing studding.







    share|improve this answer












    share|improve this answer



    share|improve this answer










    answered 2 hours ago









    Michael Karas

    43.3k43482




    43.3k43482












    • This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
      – noybman
      31 mins ago


















    • This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
      – noybman
      31 mins ago
















    This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
    – noybman
    31 mins ago




    This is where I was hinting at, but wasnt sure what was being implied by adding another stud inside. Your approach is how I've seen it done typically, and if in a utility area (hot water tank) its not an eyesore
    – noybman
    31 mins ago












    up vote
    1
    down vote













    I would fit two 2x6 (or larger) blocks crossways between your studs at the two mounting locations. Put three 3" construction (not black drywall) screws through the studs into each end of the blocks. Pilot through the studs to avoid splitting. You won't need to pilot into the end-grain of the blocks unless they're very hard wood.



    ___________________________________
    ___________________________________
    | |* | |* <-- toenail screws or angle brackets
    | | | |
    | | | |
    | | | |
    | |______________________| |
    | | | |*
    | | 2x6 block | |* <-- three screws
    | |______________________| |*
    | | | |
    | | | |
    | | | |


    This will easily carry your heater. The only weakness at this point is the connection of each stud to the top plate. you might add toenailed screws or angle brackets there.



    You could also lay in two 2x6 studs, flatwise, tight to each 2x3 stud in the bay where you'll mount the heater. This would give more horizontal stiffness if you feel like your studs are too flexible. Run screws through the 2x3 studs every foot or so.



    ___________________________________
    ___________________________________
    | | | | | |
    | | | | | |
    | | 2x6 | | 2x6 | |
    | | | | | |
    | | | | | |





    share|improve this answer



























      up vote
      1
      down vote













      I would fit two 2x6 (or larger) blocks crossways between your studs at the two mounting locations. Put three 3" construction (not black drywall) screws through the studs into each end of the blocks. Pilot through the studs to avoid splitting. You won't need to pilot into the end-grain of the blocks unless they're very hard wood.



      ___________________________________
      ___________________________________
      | |* | |* <-- toenail screws or angle brackets
      | | | |
      | | | |
      | | | |
      | |______________________| |
      | | | |*
      | | 2x6 block | |* <-- three screws
      | |______________________| |*
      | | | |
      | | | |
      | | | |


      This will easily carry your heater. The only weakness at this point is the connection of each stud to the top plate. you might add toenailed screws or angle brackets there.



      You could also lay in two 2x6 studs, flatwise, tight to each 2x3 stud in the bay where you'll mount the heater. This would give more horizontal stiffness if you feel like your studs are too flexible. Run screws through the 2x3 studs every foot or so.



      ___________________________________
      ___________________________________
      | | | | | |
      | | | | | |
      | | 2x6 | | 2x6 | |
      | | | | | |
      | | | | | |





      share|improve this answer

























        up vote
        1
        down vote










        up vote
        1
        down vote









        I would fit two 2x6 (or larger) blocks crossways between your studs at the two mounting locations. Put three 3" construction (not black drywall) screws through the studs into each end of the blocks. Pilot through the studs to avoid splitting. You won't need to pilot into the end-grain of the blocks unless they're very hard wood.



        ___________________________________
        ___________________________________
        | |* | |* <-- toenail screws or angle brackets
        | | | |
        | | | |
        | | | |
        | |______________________| |
        | | | |*
        | | 2x6 block | |* <-- three screws
        | |______________________| |*
        | | | |
        | | | |
        | | | |


        This will easily carry your heater. The only weakness at this point is the connection of each stud to the top plate. you might add toenailed screws or angle brackets there.



        You could also lay in two 2x6 studs, flatwise, tight to each 2x3 stud in the bay where you'll mount the heater. This would give more horizontal stiffness if you feel like your studs are too flexible. Run screws through the 2x3 studs every foot or so.



        ___________________________________
        ___________________________________
        | | | | | |
        | | | | | |
        | | 2x6 | | 2x6 | |
        | | | | | |
        | | | | | |





        share|improve this answer














        I would fit two 2x6 (or larger) blocks crossways between your studs at the two mounting locations. Put three 3" construction (not black drywall) screws through the studs into each end of the blocks. Pilot through the studs to avoid splitting. You won't need to pilot into the end-grain of the blocks unless they're very hard wood.



        ___________________________________
        ___________________________________
        | |* | |* <-- toenail screws or angle brackets
        | | | |
        | | | |
        | | | |
        | |______________________| |
        | | | |*
        | | 2x6 block | |* <-- three screws
        | |______________________| |*
        | | | |
        | | | |
        | | | |


        This will easily carry your heater. The only weakness at this point is the connection of each stud to the top plate. you might add toenailed screws or angle brackets there.



        You could also lay in two 2x6 studs, flatwise, tight to each 2x3 stud in the bay where you'll mount the heater. This would give more horizontal stiffness if you feel like your studs are too flexible. Run screws through the 2x3 studs every foot or so.



        ___________________________________
        ___________________________________
        | | | | | |
        | | | | | |
        | | 2x6 | | 2x6 | |
        | | | | | |
        | | | | | |






        share|improve this answer














        share|improve this answer



        share|improve this answer








        edited 2 hours ago

























        answered 3 hours ago









        isherwood

        44.3k453114




        44.3k453114






























            draft saved

            draft discarded




















































            Thanks for contributing an answer to Home Improvement Stack Exchange!


            • Please be sure to answer the question. Provide details and share your research!

            But avoid



            • Asking for help, clarification, or responding to other answers.

            • Making statements based on opinion; back them up with references or personal experience.


            To learn more, see our tips on writing great answers.





            Some of your past answers have not been well-received, and you're in danger of being blocked from answering.


            Please pay close attention to the following guidance:


            • Please be sure to answer the question. Provide details and share your research!

            But avoid



            • Asking for help, clarification, or responding to other answers.

            • Making statements based on opinion; back them up with references or personal experience.


            To learn more, see our tips on writing great answers.




            draft saved


            draft discarded














            StackExchange.ready(
            function () {
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fdiy.stackexchange.com%2fquestions%2f152798%2f16-center-bracket-to-24-center-framing%23new-answer', 'question_page');
            }
            );

            Post as a guest















            Required, but never shown





















































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown

































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown







            Popular posts from this blog

            flock() on closed filehandle LOCK_FILE at /usr/bin/apt-mirror

            Mangá

            Eduardo VII do Reino Unido